Transparency

This is an experiment in living and life for us. And two of the keys of good science are documentation and an ability to duplicate the results. We’ll be outlining exactly how we made all of this a reality (being as transparent as possible along the way). One facet of this will be outlying all costs so that people can budget/plan aspects of this work on their own more effectively.

And I’d like to reiterate, while I believe this is a good path for us and possibly you, it is not for everyone and if you would really like to make a difference in a green/sustainable/significant way, cities are the place to start. That being said, if you plan on starting your own thing… these costs could be used as a general guideline.

We’re working on getting all expenses detailed here*:

DateItemCategoryAmount
6/23/2009Concrete FinishingFoundation$1,041.60
6/6/2008Building PermitPermits$2,003.81
6/6/2008SA (Site Application?)Permits$30.00
6/6/2008Forestry WaiverPermits$100.00
6/6/2008Septic ApplicationPermits$300.00
10/2/2009Roof and Wainscoting (Materials and Labor)Roofing$15,327.62
10/2/2009Drip edge (custom)Siding$436.75
6/5/20093/4 Washed RockFoundation$210.44
6/5/20093/4 Washed RockFoundation$209.88
6/5/2009Top CoarseFoundation$215.66
6/4/2009Top CoarseFoundation$866.32
6/4/2009Top CoarseFoundation$212.14
6/4/2009Top CoarseFoundation$214.96
6/4/2009Top CoarseFoundation$222.01
6/4/2009Top CoarseFoundation$213.12
6/4/2009Pea GravelLandscaping$208.79
6/15/2009Tie Bag Wire 8"Foundation$18.36
7/31/2009Deck/Siding/Trim LaborSiding$5,417.61
6/11/2009Plumbing/RadonPlumbing$1,371.90
6/5/2009CompactorFoundation$174.20
6/15/2009CompactorFoundation$87.11
6/15/20096x6's Glu-LamLumber$169.52
6/4/2009Pier Forms/Glu-Lam (returns?)Lumber-$139.64
6/15/2009Rebar/Tie wireFoundation$55.64
6/2/2009Pier Forms/Sono TubeHardware$383.08
6/15/20096 Mil VisqueenFoundation$61.98
6/22/2009Carriage BoltsHardware$34.54
7/15/2009Chimney (Materials and Labor)Chimney$2,120.90
7/28/2009FastenersHardware$36.96
7/28/2009LumberLumber$107.40
7/28/2009LumberLumber$419.19
7/24/2009Garage DoorGarage Door$1,070.62
7/9/2009Framing/Install Windows (Labor)Framing$7,891.62
6/29/2009TrussesLumber$6,560.24
6/26/2009Glulam JoistLumber$261.77
7/3/20092X10'SLumber$484.67
7/2/2009GlulamLumber$25.51
7/7/20092x6'sLumber$96.52
7/8/20092x12's and Glulam postsLumber$599.21
7/10/2009Tie downsHardware$47.11
7/13/20092x10Lumber$47.67
7/14/20092x10Lumber$54.11
5/13/2009Hardware for sliding barn doorHardware$730.87
5/13/2009Hardy TrimSiding$194.82
5/14/2009Exterior LightsElectrical$739.75
5/27/2009Entry DoorFront Door$1,175.26
5/29/2009Grading/Foundation WorkFoundation$9,254.68
5/20/2009CupolaLumber$853.90
7/3/2008Trencher rentalPower$934.20
5/5/2008Power pedestal installationPower$2,423.50
4/22/2009Pump installationWell$6,588.45
4/14/2009Well DrillingWell$6,264.47
3/3/2009Septic DesignSeptic$650.00
6/28/2008Equipment rental - mini excavatorSeptic$363.96
Total:$79,444.76
1/6/2010Delivery of Flooring and Extra BacksplashFlooring$1,336.00