This is an experiment in living and life for us. And two of the keys of good science are documentation and an ability to duplicate the results. We’ll be outlining exactly how we made all of this a reality (being as transparent as possible along the way). One facet of this will be outlying all costs so that people can budget/plan aspects of this work on their own more effectively.
And I’d like to reiterate, while I believe this is a good path for us and possibly you, it is not for everyone and if you would really like to make a difference in a green/sustainable/significant way, cities are the place to start. That being said, if you plan on starting your own thing… these costs could be used as a general guideline.
We’re working on getting all expenses detailed here*:
Date Item Category Amount
6/23/2009 Concrete Finishing Foundation $1,041.60
6/6/2008 Building Permit Permits $2,003.81
6/6/2008 SA (Site Application?) Permits $30.00
6/6/2008 Forestry Waiver Permits $100.00
6/6/2008 Septic Application Permits $300.00
10/2/2009 Roof and Wainscoting (Materials and Labor) Roofing $15,327.62
10/2/2009 Drip edge (custom) Siding $436.75
6/5/2009 3/4 Washed Rock Foundation $210.44
6/5/2009 3/4 Washed Rock Foundation $209.88
6/5/2009 Top Coarse Foundation $215.66
6/4/2009 Top Coarse Foundation $866.32
6/4/2009 Top Coarse Foundation $212.14
6/4/2009 Top Coarse Foundation $214.96
6/4/2009 Top Coarse Foundation $222.01
6/4/2009 Top Coarse Foundation $213.12
6/4/2009 Pea Gravel Landscaping $208.79
6/15/2009 Tie Bag Wire 8" Foundation $18.36
7/31/2009 Deck/Siding/Trim Labor Siding $5,417.61
6/11/2009 Plumbing/Radon Plumbing $1,371.90
6/5/2009 Compactor Foundation $174.20
6/15/2009 Compactor Foundation $87.11
6/15/2009 6x6's Glu-Lam Lumber $169.52
6/4/2009 Pier Forms/Glu-Lam (returns?) Lumber -$139.64
6/15/2009 Rebar/Tie wire Foundation $55.64
6/2/2009 Pier Forms/Sono Tube Hardware $383.08
6/15/2009 6 Mil Visqueen Foundation $61.98
6/22/2009 Carriage Bolts Hardware $34.54
7/15/2009 Chimney (Materials and Labor) Chimney $2,120.90
7/28/2009 Fasteners Hardware $36.96
7/28/2009 Lumber Lumber $107.40
7/28/2009 Lumber Lumber $419.19
7/24/2009 Garage Door Garage Door $1,070.62
7/9/2009 Framing/Install Windows (Labor) Framing $7,891.62
6/29/2009 Trusses Lumber $6,560.24
6/26/2009 Glulam Joist Lumber $261.77
7/3/2009 2X10'S Lumber $484.67
7/2/2009 Glulam Lumber $25.51
7/7/2009 2x6's Lumber $96.52
7/8/2009 2x12's and Glulam posts Lumber $599.21
7/10/2009 Tie downs Hardware $47.11
7/13/2009 2x10 Lumber $47.67
7/14/2009 2x10 Lumber $54.11
5/13/2009 Hardware for sliding barn door Hardware $730.87
5/13/2009 Hardy Trim Siding $194.82
5/14/2009 Exterior Lights Electrical $739.75
5/27/2009 Entry Door Front Door $1,175.26
5/29/2009 Grading/Foundation Work Foundation $9,254.68
5/20/2009 Cupola Lumber $853.90
7/3/2008 Trencher rental Power $934.20
5/5/2008 Power pedestal installation Power $2,423.50
4/22/2009 Pump installation Well $6,588.45
4/14/2009 Well Drilling Well $6,264.47
3/3/2009 Septic Design Septic $650.00
6/28/2008 Equipment rental - mini excavator Septic $363.96
Total: $79,444.76
1/6/2010 Delivery of Flooring and Extra Backsplash Flooring $1,336.00