It’s been a busy busy first 5 weeks here at Moosicorn. We are now into week 6 and are currently working on electrical rough-in. Here’s a brief recap (mostly in pictures) of what’s go on so far.
First thing we had done after arriving was getting internet installed, because hey, we have our priorities…
Second was plumbing rough-in and framing changes…
Then came central vac install and radiant piping install which we did ourselves…
We squeezed in getting a little garden started…
Next came finishing the trenching for the internet cable into the house…
Then we worked on venting out the 3 exhaust fans…
Somewhere in between this all we got our compost started…
And we helped the survey guy get the property lines marked…
And now we’re in the middle of electrical rough-in…
We’ve also been fixing the tractor, situating camp, enjoying the outdoors and doting on the dog… She’s loving it out here! Next up will be electrical inspection (keep your fingers crossed), insulation, drywall… and then all the fun finishing work, that I’m really looking forward to.


WOW, has it been 6 weeks already?! You two sure have been busy! I’ve been loving all of the pics and updates.